Skip to content
MCS · Ledger

Hut 8

Hut 8 Corp

Seam
Mining to HPC
Status
Mainnet
Live since
2018
Verified
2026-09-12

Building to NVIDIA reference architecture, which is the tell that this is no longer a mining company.

Project site ↗

Sourced figures

  • Contracted IT capacity352 MW

    Megawatts of datacentre IT load the operator has under signed contract for HPC or AI hosting.

    Beacon Point, Nueces County TX — a 15-year, $9.8B lease. Lifts total contracted AI capacity to roughly 597 MW.

    Source ↗

The silicon

  • NVIDIA DSX facility

    NVIDIA

    Beacon Point is built to the NVIDIA DSX reference architecture rather than retrofitted from mining halls, which is the structural difference between a pivot and a rebrand.

    Source ↗